BMW X5 (G05) 2019-2024 Service & Repair Manual / Body / Wheel Wells / Replacing Front Left Wheel Arch

Read contents of Body, General. The steel-aluminum mixed construction is used on the vehicle.

Observe specific procedure.

Remove or cover those vehicle components in the repair area which are susceptible to heat or dust.

Use only approved spot-welding apparatus for repairs.

Place vehicle on straightening bench.

Following new body parts are required:

  1. Wheel arch, front
  2. Reinforcement, support carrier

Wheel Wells
Fig. 100: Identifying Reinforcement, Support Carrie

Open weld joints in area (1).

Wheel Wells
Fig. 101: Identifying Weld Parts Area

Open weld joints in areas (1).

Wheel Wells
Fig. 102: Identifying Weld Parts Area

Open weld joints in area (1).

Wheel Wells
Fig. 103: Identifying Open Weld Joints Area

Mark severance cut in accordance with measurement a and cut support carrier.

Measurement a=50 mm before 20 mm dia. bore

Open weld joints in area (1).

Installation:

Weld in reinforcement plate at severance cut.

Wheel Wells
Fig. 104: Identifying Open Weld Joints Area

Open weld joints in area (1).

Wheel Wells
Fig. 105: Identifying Open Weld Joints Area

Drill out riveted joints in areas (1) and (2).

Open adhesive joints in areas (1) to (3).

Installation:

Adjust new part to fit with straightening attachment or universal mount.

Use 19 rivets (size 815) in area (1).

Use 4 rivets (size 815) in area (2).

Wheel Wells
Fig. 106: Identifying Open Adhesive Joints Areas

Installation:

For accessibility reasons, move rivet (1) 15 mm forwards (2).

Wheel Wells
Fig. 107: Identifying Rivet

READ NEXT:

 Replacing Complete Rear Left Wheel Arch (Rear Left Side Panel Removed)

Read contents of Body, General. Spot-weld bonding is used on this vehicle. Observe specific procedure. Remove or cover those vehicle components in the repair area which are susceptible to heat or d

 Replacing Rear Left Outer Wheel Arch Section (Rear Left Side Panel Removed)

Read contents of Body, General. Spot-weld bonding is used on this vehicle. Observe specific procedure. Remove or cover those vehicle components in the repair area which are susceptible to heat or d

 Side Frame And Door

SEE MORE:

 Emissions Management

The N54 and N52KP meet ULEV II requirements for 2007. There are not many changes to the emission systems on these engines. The N54 engine has 2 underbody catalysts in addition to the "near engine" catalysts already in use from the N52. The N51 engine, however, is a SULEV II compliant engine which

 Mufflers, Petrol

REPLACING REAR MUFFLER (N52K) Special tools required: 00 2 210 31 2 220 WARNING: Scalding hazard! Only perform these tasks after exhaust system has cooled down. Support exhaust system with special tool 31 2 220. Fig. 8: Identifying Special Tool (31 2 220) NOTE: If the cutting lines are not id